WARNING: Incorrect wiring of a 380V industrial ultrasonic cleaner can cause equipment failure, electric shock, or fire. Always consult a certified electrician before installation.


1. Pre-Wiring Preparations

1.1 Verify Electrical Requirements

Before connecting, ensure your power supply matches the machine’s specifications:

Parameter Industrial Standard Testing Method
Voltage 380V ±10% (3-phase) Multimeter (phase-to-phase)
Current Rating ≥1.5x machine power (e.g., 5kW → 16A breaker) Check circuit breaker
Grounding ≤4Ω resistance Earth resistance tester
Wire Gauge ≥2.5mm² copper (for 5kW+) Check cable markings

1.2 Required Tools & Safety Gear

  • Essential Tools:
    • Insulated screwdrivers
    • Wire strippers
    • Multimeter
    • Torque wrench (for terminal tightening)
  • Safety Equipment:
    • 1000V insulated gloves
    • Safety goggles
    • Fire extinguisher (Class C for electrical fires)


2. Step-by-Step Wiring Instructions

2.1 Identify Wire Colors (IEC Standard)

Wire Type Color Code Terminal Label
Phase 1 (L1) Brown L1
Phase 2 (L2) Black L2
Phase 3 (L3) Gray L3
Neutral (N) Blue N
Ground (PE) Green/Yellow ⏚ (Earth symbol)

⚠️ Never rely on color alone—always verify with a multimeter!

2.2 Terminal Connection Procedure

  1. Power Off – Disconnect the main supply and lock out (LOTO).
  2. Open the Junction Box – Typically located at the rear of the machine.
  3. Secure Grounding First – Connect the green/yellow wire to the earth terminal (most critical for safety).
  4. Connect Neutral (N) – Attach the blue wire to the neutral terminal.
  5. Connect Phases (L1/L2/L3) – Match brown, black, and gray wires to their respective terminals.
  6. Torque Terminals – Tighten to 1.2 N·m (over-tightening can damage threads).
  7. Cable Strain Relief – Use clamps to prevent wire pullout.

2.3 Post-Wiring Safety Checks

Test Acceptable Value Tool
Insulation Resistance ≥10 MΩ (phase-to-ground) Megohmmeter
Voltage Balance ≤5% deviation (L1/L2/L3) Multimeter
Leakage Current ≤3.5 mA Clamp meter


3. Common Wiring Mistakes & How to Avoid Them

❌ Mistake 1: Swapping Neutral & Ground

  • Risk: Electrocution + PCB damage
  • Fix: Use different-colored heat shrink tubes (blue for neutral, green/yellow for ground).

❌ Mistake 2: Loose Terminal Connections

  • Result: Arcing, overheating, fire hazard
  • Solution: Apply anti-oxidation paste and retighten after 24 hours.

❌ Mistake 3: Incorrect Phase Sequence

  • Symptom: Pump/motor runs backward
  • Test: Use a phase rotation meter before powering on.


4. Advanced Wiring for Smart Cleaners (PLC/Modbus Models)

4.1 Control Wiring (Low Voltage Side)

Signal Type Wire Specification Connection
Temperature Sensor PT100 (3-wire) TEMP+/TEMP-/GND
Water Level Sensor 24V DC (2-wire) LV+/LV-
Emergency Stop Normally Closed (NC) E-STOP circuit

4.2 Noise Prevention Tips

  • Use shielded twisted-pair cables for sensors.
  • Keep signal wires ≥30cm away from power cables.
  • Ground the shield at one end only (controller side).


5. First Power-On & Commissioning

  1. Dry Run Test (No water) – Check for abnormal vibrations/noise.
  2. Load Test (With water) – Verify current draw matches the nameplate.
  3. Function Test – Confirm heating, timer, and ultrasonic activation.

Pro Tip: Record startup current with a clamp meter—spikes above 125% rated current indicate a fault.


Final Safety Reminder

  • Never modify wiring without disconnecting power.
  • Label all terminals clearly for future maintenance.
  • Schedule annual insulation resistance tests.